The area beneath the concrete block was dugout to a depth of 400mm and crushed rocked placed and compacted with the blunt end of a crow bar. In order to stop the double concrete blocks from moving away from each other, they were glued utilising "liquid nails".
Sub-frame has been nogged out with additional floor joist placed at 450mm centers and whole structure is quite rigid.
Love the nail gun.
Concrete blocks have been liquid nailed together and are placed on compacted crushed rock. |